Milestones:
2003
March
CSU Board of Trustees' conceptual approval (March 11)
Initial Campus Workshops
  Brizzolara Creek (March 21)
  Auxiliaries and Services (March 28)
April
Preliminary Conceptual Plan (April 2)
Campus Planning Committee (April 10)
Continuing Campus Workshops
  Envisioning a 21st-Century Residential Learning Community
(April 18)
  The Built Form (April 30)
Scope of Environmental Review (April 28)
Market Study
 
May
Continuing Campus Workshops
  Landscape Design and Spatial Connections with Campus Core (May 15)
Preliminary Schematic Design
 
June
Release of Draft Environmental Impact Report (DEIR) for comment
Continuing Campus Workshops
  Circulation Options and Impacts (June 4)
    Click to see circulation options: Option 2
Design Development

July
Final EIR and Response to comments on Draft EIR
Drawings and Specifications

Campus Planning Committee (July 23)

August
Campus Planning Committee (August 21)

September
CSU Board of Trustees’ approval of Schematic Design and Final EIR


2004
April
Program Manager Request for Qualifications advertised

June
Program Manager Statements of Qualifications received

July
Brookwood Program Management of Atlanta, Georgia selected

September
Design-Build Team Short List of qualified firms identified


2005
January
Design-Build Request for Proposals released to short list

May
Financing approved by Board of Trustees

June

Contract awarded to Clark Design/Build of California, Inc.
Architect: Niles Bolton of Atlanta, Georgia