Milestones:
| 2003 |
| March |
| CSU Board of Trustees'
conceptual approval (March 11) |
| Initial Campus Workshops |
| |
Brizzolara Creek (March
21) |
| |
Auxiliaries and Services (March 28) |
| April |
| Preliminary
Conceptual Plan (April 2) |
| Campus Planning Committee
(April 10) |
| Continuing Campus Workshops |
| |
Envisioning a 21st-Century
Residential Learning Community
(April 18) |
| |
The Built Form (April 30) |
| Scope of Environmental
Review (April 28) |
| Market Study |
| |
| May |
| Continuing Campus Workshops |
| |
Landscape Design and Spatial
Connections with Campus Core (May 15) |
| Preliminary Schematic Design |
| |
| June |
| Release of Draft Environmental
Impact Report (DEIR) for comment |
| Continuing Campus Workshops |
| |
Circulation Options and
Impacts (June 4) |
| |
|
Click to see circulation
options: |
|
Option
2 |
| Design Development |
July
Final EIR and Response to comments on Draft EIR
Drawings and Specifications
Campus Planning Committee (July 23)
August
Campus Planning Committee (August 21)
| September |
| CSU Board of Trustees’ approval
of Schematic Design and Final EIR |
2004
| April |
| Program Manager
Request for Qualifications advertised |
| June |
| Program Manager
Statements of Qualifications received |
| July |
| Brookwood Program
Management of Atlanta, Georgia selected |
| September |
| Design-Build
Team Short List of qualified firms identified |
2005
| January |
| Design-Build
Request for Proposals released to short list |
| May |
| Financing approved
by Board of Trustees |
| June |
Contract
awarded to Clark Design/Build of California, Inc.
Architect: Niles Bolton of Atlanta, Georgia |
|